| 90 |
Merced to Madera Civil Works contract preparation |
HSR Procurements |
Jun 02 |
| 75 |
Program Delivery Partner (PDP) scope development underway |
HSR Procurements |
Jun 02 |
| 95 |
Architectural & Engineering IDIQ pending qualifications |
HSR Procurements |
Jun 02 |
| 90 |
Multiple Award Task Order Contract (MATOC) nearing award |
HSR Procurements |
Jun 02 |
| 80 |
Power Generation Public-Private Partnership RFEI |
HSR Procurements |
Jun 02 |
| 90 |
Co-Development Agreement (CDA) active procurement |
HSR Procurements |
Jun 02 |
| 100 |
Track & Systems Construction Contract (TSCC) active solicitation |
HSR Procurements |
Jun 02 |
| 100 |
Materials Procurement active contract upcoming |
HSR Procurements |
Jun 02 |
| 85 |
$3.5 Billion Track and Systems RFP Released |
HSR Newsroom |
Jun 02 |
| 80 |
Private investor engagement process launched |
HSR Newsroom |
Jun 02 |
| 80 |
Major track and systems contract awarded to Kiewit-Stacey Witbeck-Herzog consortium |
HSR Newsroom |
Jun 02 |
| 100 |
$3.5 billion track and systems procurement launched |
HSR Newsroom |
May 31 |
| 75 |
2026 Business Plan Adoption |
CHSRA Board Materials |
May 30 |
| 90 |
Multiple major procurements finalizing awards |
HSR Procurements |
May 30 |
| 75 |
Program Delivery Partner procurement in development |
HSR Procurements |
May 30 |
| 90 |
AE IDIQ contract pending qualification submissions |
HSR Procurements |
May 30 |
| 80 |
Power Generation P3 RFEI scheduled for 2026 |
HSR Procurements |
May 30 |
| 90 |
Co-Development Agreement procurement launching |
HSR Procurements |
May 30 |
| 100 |
Track & Systems Construction Contract solicitation imminent |
HSR Procurements |
May 30 |
| 80 |
Construction Package 2-3 Change Order Settlement |
CHSRA Board Materials |
May 29 |
| 75 |
Architect Engineer IDIQ Pool Contract Release |
CHSRA Board Materials |
May 29 |
| 90 |
Cable Trough Materials Contract Award |
CHSRA Board Materials |
May 29 |
| 90 |
Multiple major civil works contracts in pipeline |
HSR Procurements |
May 29 |
| 50 |
Los Angeles to Anaheim environmental review underway |
HSR Newsroom |
May 29 |
| 100 |
$3.5 billion track and systems RFP launched |
HSR Newsroom |
May 29 |