Track Systems · Procurement · Central Valley (119-mile First Construction Section + Extensions)

Project Details

CHSRA

—

$3.5B (not-to-exceed)

Hybrid

State

RFP issued Nov 2025; proposals received; board approval to award anticipated June 2026

TSCC Track & Systems Construction Contract Track and Systems Construction Track and Systems track/systems contract 119-mile

Linked Signals (244)

Score Title Source Date
95 Trainsets Procurement Still Active — Award TBD HSR Procurements Aug 31
65 Maintenance Facility and Operations Control Center — Upcoming, TBD Timeline HSR Procurements Aug 31
85 Locally Generated Alternative Progressive Design-Build — Scope Developing, Award Q1/Q2 2027 HSR Procurements Aug 31
100 Merced to Madera Civil Works RFQ Active — Shortlist Expected Q4 2026 HSR Procurements Aug 31
95 MATOC On-Ramp for Small Business Pool — Q4 2026 Solicitation HSR Procurements Aug 31
100 Materials Procurement Active — Award Window January–May 2026 HSR Procurements Aug 31
85 2026 Business Plan Adopted — Program Baseline and Budget Established CHSRA Board Materials resurfaced Aug 26
95 Trainsets Procurement — Active, Award TBD HSR Procurements Aug 25
65 Maintenance Facility/OCC and Tunnels — Upcoming, TBD Timeline HSR Procurements Aug 25
85 Locally Generated Alternative Progressive Design-Build — Scope Development, Award Q1/Q2 2027 HSR Procurements Aug 25
100 Cal CLEAN Partnership Agreement — Active Procurement, Award Q1 2027 HSR Procurements Aug 25
95 MATOC On-Ramp (Small Business Pool) — Q4 2026 Solicitation HSR Procurements Aug 25
80 Program Delivery Partner (PDP) — Scope Development, Award Late 2027 HSR Procurements Aug 25
95 AE IDIQ Under Evaluation — Award Q3 2026 HSR Procurements Aug 25
100 Materials Procurement — Active Solicitation, Award Jan–May 2026 HSR Procurements Aug 25
95 Track and Systems Contract Awarded to Kiewit, Stacy Witbeck, and Herzog Consortium HSR Newsroom Aug 22
100 CA HSR Drops Buy America Requirements Industry News Aug 20
95 Track and Systems Construction Contract Awarded (HSR25-89) CHSRA Board Materials Aug 19
95 CA HSR Inspector General warns project may exhaust funds by end of 2027 Industry News Aug 15
95 CA HSR Faces Funding Exhaustion by 2027 per Inspector General Warning Industry News Aug 15
80 CA HSR funding exhaustion projected by December 2027 Industry News resurfaced Aug 14
80 CA HSR Central Valley construction shifting to track installation phase Industry News Aug 14
85 CA HSR Funding Exhaustion Projected by December 2027 Industry News Aug 14
85 CA HSR Projected to Exhaust Funds by 2027 Industry News Aug 13
85 Cable Trough Materials Contract Awarded (HSR25-117) CHSRA Board Materials Aug 12