← Back to signals
100

HSR Materials Procurement Portfolio — Up to $507.1M NTP 1 Value

procurement confirmed act_now
HSR Procurements · Jul 10

Summary

CHSRA is actively procuring track and systems materials for the 119-mile First Construction Section, with cumulative NTP 1 contract value not-to-exceed $507.1 million. Contracts for Long Welded Rail (HSR 25-26), Concrete Ties (HSR 25-27), and OCS Poles (HSR 25-25) have been awarded; Notice of Proposed Award issued for Cable Troughs (HSR 25-117); and Ballast (HSR 25-28) NOPA issued June 2026.

Details

Multiple awarded and near-award contracts represent immediate supplier and subcontractor opportunities for compliant rail materials manufacturers and distributors.

CHSRA directing up to $507.1M toward rail materials suppliers for NTP 1; additional NTP 2 and NTP 3 options for northern and southern extensions

California High-Speed Rail Authority

View at source →