← Back to projects

Central Valley Station Design (4 stations)

Station · Design · Merced, Fresno, Kings/Tulare, Bakersfield

Project Details

CHSRA

Foster + Partners / Arup

~$35M (Phase 1 design)

Professional Services

Station construction anticipated mid-2026 to mid-2029

CV Station Design Central Valley stations Foster Partners F+P Arup Merced station Fresno station Bakersfield station Kings Tulare station Hanford station

Linked Signals (73)

Score Title Source Date
90 Multiple major capital procurements planned for 2025-2026 HSR Procurements May 13
90 Fresno Station Early Works construction contract releasing December 2025 HSR Procurements May 13
90 MATOC task order contracting framework established HSR Procurements May 09
70 Clean Energy Delivery Program market research launched HSR Procurements May 09
90 Multiple major design-build and construction procurements in 2025-2026 HSR Procurements May 09
100 Fresno Station Early Works construction contract imminent HSR Procurements May 09
90 Co-Development Agreement (CDA) procurement launching December 2025 HSR Procurements May 09
100 Fresno Station Early Works active procurement HSR Procurements May 09
100 Materials Procurement launching Q3/Q4 2025 HSR Procurements May 09
70 Program Delivery Partner scope development underway HSR Procurements May 09
95 Architectural & Engineering IDIQ accepting qualifications HSR Procurements May 09
100 Multiple Award Task Order Contract finalizing award HSR Procurements May 09
80 Power Generation Public-Private Partnership RFI in Q1 2026 HSR Procurements May 09
80 Co-Development Agreement procurement December 2025 HSR Procurements May 09
95 Track & Systems Construction Contract solicitation November 2025 HSR Procurements May 09
75 Draft 2026 Business Plan cost reduction CHSRA Website May 09
80 Private investor engagement process initiated CHSRA Website May 09
85 Draft 2026 Business Plan released for public review CHSRA Website May 04
100 $3.5 billion track and systems contract released to market CHSRA Website May 04
90 Authority launches private investment partner selection process CHSRA Website May 04
75 Draft 2026 Business Plan released for review CHSRA Website May 04
80 Private investor recruitment process initiated CHSRA Website May 04
100 $3.5 billion track and systems RFP launched CHSRA Website May 04