CP 1 — Construction Package 1 (Madera to Fresno)
Construction
· Construction
· Madera & Fresno Counties
Project Details
CHSRA
Tutor Perini / Zachry / Parsons (TPZP)
~$3.8B
Design Build
State
20 of 33 structures complete, substantial completion targeted end of 2026
CP 1 CP1 Construction Package 1 Madera to Fresno TPZP Tutor Perini
Linked Signals (34)
| Score | Title | Source | Date |
|---|---|---|---|
| 85 | $2.4B Merced-to-Madera HSR Extension Moving Forward | Industry News | Jul 05 |
| 100 | CHSRA Issues RFQ for Merced-Madera Civil Works Package | Industry News | Jul 05 |
| 100 | CHSRA Posts Major Design-Build Solicitation: M2M Collaborative Design-Build Services | Cal eProcure CHSRA | Jul 05 |
| 95 | CHSRA Solicitation: As-Needed Goat Grazing Services for Vegetation Management | Cal eProcure CHSRA | Jul 05 |
| 95 | CHSRA Issues Solicitation for M2M Collaborative Design-Build Services | Cal eProcure CHSRA | Jul 05 |
| 90 | CHSRA Solicitation: M2M Collaborative Design-Build Services (HSR26-16) | Cal eProcure CHSRA | Jul 05 |
| 100 | CA HSR Launches Major Construction Procurement for Merced to Madera Extension | Industry News | Jul 05 |
| 80 | Valley Rail Program Component Modifications | CTC Meeting Agendas | Jun 13 |
| 85 | High Desert Intercity High-Speed Rail Corridor time extension request | CTC Meeting Agendas | May 09 |