90

Co-Development Agreement procurement launching

CDA solicitation scheduled for December 2025 with award targeted for June 2026

p3 confirmed act_now
HSR Procurements
May 30
100

Track & Systems Construction Contract solicitation imminent

TSCC solicitation scheduled for November 2025 with tentative award in June 2026

procurement confirmed act_now
HSR Procurements
May 30
45

Proposed law may keep CA HSR records secret

A proposed law could allow some California high-speed rail records to remain confidential, potentially affecting transparency and oversight of the project.

government early_signal watch
Industry News
May 29
90

California HSR cuts $1.7B from 2026 budget

California High-Speed Rail Authority has reduced its 2026 budget by $1.7 billion according to news reports

funding confirmed act_now
Industry News
May 29
100

Fire safety systems maintenance contract for 9 CHSRA Fresno properties

CHSRA issued IFB HSR25-124 for fire alarm suppression systems and fire sprinkler systems monitoring, maintenance and repair services for nine properties in Fresno, with bids due June 3, 2026.

procurement confirmed act_now
Cal eProcure CHSRA
May 29
45

CA HSR Authority misses planning deadline

California High-Speed Rail Authority has missed a deadline for submitting a required plan, though specific details of the plan type and consequences are not provided in the summary.

government early_signal watch
Industry News
May 29
40

Eminent Domain Appraisal Reform - Potential Land Acquisition Impact

AB1752 passed the Assembly (77-0) and moved to Senate, addressing eminent domain appraisal procedures. This legislation could affect how CHSR acquires right-of-way and property, potentially impacting …

general early_signal watch
CA Legislative Info
May 29
80

Construction Package 2-3 Change Order Settlement

CHSRA Board approved Change Order #427 for Construction Contract 2-3 as DFJV settlement.

procurement confirmed background
CHSRA Board Materials
May 29
75

Architect Engineer IDIQ Pool Contract Release

CHSRA approved release of Request for Qualifications (RFQ) for Architectural & Engineering services for Indefinite Delivery Indefinite Quantity pool contracts in March 2026.

consultant_need confirmed background
CHSRA Board Materials
May 29
90

Cable Trough Materials Contract Award

Board approved cable trough materials contract HSR25-117 in April 2026

procurement confirmed watch
CHSRA Board Materials
May 29
80

Active MATOC contracts generating task orders

Multiple Award Task Order Contract established with Small Business, Utility, and Large Business pools, currently executing task orders including Semitropic Well Abandonment ($55,119) and Canal 9-22 Ea…

procurement confirmed background
HSR Procurements
May 29
85

A&E services indefinite delivery contract opportunity

Architectural & Engineering IDIQ contract to release March 2026 with Q3 2026 award for ongoing design and engineering services

consultant_need confirmed watch
HSR Procurements
May 29
90

HSR Materials procurement launching

Procurement of HSR Materials to release Q3/Q4 2025 with awards January-May 2026

procurement confirmed watch
HSR Procurements
May 29
90

Multiple major civil works contracts in pipeline

Merced to Madera Civil Works RFQ scheduled July 2026, RFP TBD with Q4 2027 award, and Track & Systems Construction Contract releasing November 2025

procurement confirmed watch
HSR Procurements
May 29
100

Fresno Station Early Works construction opportunity

Fresno Station Early Works Invitation for Bid released December 10, 2025 with April 2026 tentative award

procurement confirmed act_now
HSR Procurements
May 29
90

Co-Development Agreement (CDA) procurement upcoming

Co-Development Agreement procurement to be released December 19, 2025 with tentative award June 2026

procurement confirmed watch
HSR Procurements
May 29
80

Private investor recruitment process initiated

California High-Speed Rail Authority initiated a process on December 19, 2025 to bring private investors and developers by summer 2026 to evaluate commercialization strategies and support future segme…

p3 confirmed watch
HSR Newsroom
May 29
50

Los Angeles to Anaheim environmental review underway

California High-Speed Rail Authority released Draft Environmental Impact Report/Environmental Impact Statement for the 30-mile Los Angeles to Anaheim segment in December 2025.

general strong_indicator watch
HSR Newsroom
May 29
100

$3.5 billion track and systems RFP launched

California High-Speed Rail Authority brought a $3.5 billion Request for Proposals to market for track and systems delivery on November 26, 2025.

procurement confirmed act_now
HSR Newsroom
May 29
100

Fire Safety Systems Maintenance Contract - 9 CHSRA Properties

CHSRA has posted IFB HSR25-124 for fire alarm suppression systems and fire sprinkler systems monitoring, maintenance and repair services across nine properties in Fresno, CA, with bids due March 6, 20…

procurement confirmed act_now
Cal eProcure CHSRA
May 29
45

California High-Speed Rail Authority misses plan deadline

The California High-Speed Rail Authority failed to meet a deadline for submitting a required plan, though specific details about the plan type and consequences are not provided in the available conten…

government early_signal watch
Industry News
May 29
45

California HSR Authority misses planning deadline

California High-Speed Rail Authority failed to meet a deadline for submitting a required plan, though specific details about the plan type and consequences are not provided in the available summary.

government early_signal watch
Industry News
May 29
90

Fire safety systems maintenance contract for 9 CHSRA properties in Fresno

CHSRA has issued IFB HSR25-124 for fire alarm suppression systems and fire sprinkler systems monitoring, maintenance and repair services for nine properties in Fresno, with bids due March 6, 2026.

procurement confirmed watch
Cal eProcure CHSRA
May 28
75

CHSRA advances track and systems construction procurement

California High-Speed Rail Authority is moving forward with procurement for track and systems construction components.

procurement strong_indicator watch
Industry News
May 28
65

CA HSR CEO returns to work after board review of arrest

California High-Speed Rail CEO was asked to return to work following a board review of an arrest incident.

government confirmed watch
Industry News
May 28