Procurement Modernization — CEO Delegation of Authority and RFQ/RFP Policy Revisions
The Board approved revisions to the CEO Delegation of Authority and Board RFQ/RFP Policies and Procedures at the June 24, 2026 meeting via Resolution HSRA 26-11, including a statutory provision requir…
Construction Package 2-3 Change Order #427 (DFJV Settlement) Approved
Board approved Resolution #HSR 26-06 on April 29, 2026 for Change Order #427 on Construction Contract 2-3, described as a DFJV settlement change order. This confirms active claims/settlement activity …
Merced to Madera Civil Works RFQ Release — July 2026
CAHSRA will release the Merced to Madera Civil Works RFQ in July 2026, with a shortlist and PPCA (Public Private Contract Act) decision targeted for December 2026. This is a major civil construction p…
Merced to Madera Civil Works RFP — Q4 2027 Award
Following the RFQ shortlist process, CAHSRA plans to release the full RFP for Merced to Madera Civil Works with a tentative award in Q4 2027. Release date is currently TBD.
Procurement of HSR Materials — Release Q3/Q4 2025, Award January–May 2026
CAHSRA is releasing a materials procurement in Q3/Q4 2025 with awards expected between January and May 2026, indicating near-term construction supply chain activity.
A&E IDIQ (Indefinite Delivery Indefinite Quantity) — March 2026 Release, Q3 2026 Award
CAHSRA will release a new Architectural & Engineering IDIQ contract in March 2026, with award anticipated in Q3 2026, creating a standing vehicle for ongoing A&E task orders across the program.
Trainset Procurement — Ongoing, Award TBD
The trainset procurement was released August 25, 2023, but award remains TBD, indicating the process is still active and unresolved after more than two years.
MATOC Established — Small Business, Utility, and Large Business Pools Active
CAHSRA has established a Multiple Award Task Order Contract (MATOC) under HSR25-40 with eight named awardees across three pools; three task orders have already been issued totaling approximately $8.2 …
Clean Energy Delivery Program RFEI — Active Market Research
CAHSRA released an RFEI for its Clean Energy Delivery Program on January 8, 2026, with no stated due date, seeking industry input on commercial, financial, technical, and procurement considerations to…
One-on-One Pre-Procurement Meetings Available with CAHSRA
CAHSRA actively encourages one-on-one industry meetings prior to procurement issuance, open to potential offerors, team members including small businesses, and industry representatives.
Materials Procurement Active — Award January–May 2026
HSRA has an active materials procurement solicitation in Q3/Q4 2025 with tentative award between January and May 2026.
Co-Development Agreement (CDA) Awarded
The CDA was solicited in December 2025 and has been awarded, with tentative finalization in June 2026.
Architectural & Engineering IDIQ — Pending Qualification Submissions
The AE IDIQ was solicited in March 2026 and is currently pending qualification submissions, with award expected Q3 2026.
Program Delivery Partner (PDP) Scope Under Development — Award Late 2027
HSRA is developing the scope for a Program Delivery Partner contract, with solicitation planned Q3/Q4 2026 and award in late 2027.
Maintenance Facility/OCC Procurement Upcoming — Timeline TBD
HSRA lists the Maintenance Facility and Operations Control Center procurement as upcoming with no solicitation date set.
Trainsets Procurement Active — Award TBD
The trainset procurement was initiated in 2023 and remains in active procurement status with no award date confirmed.
Merced to Madera Civil Works RFQ — Solicitation July 2026
HSRA is finalizing documentation for the Merced to Madera Civil Works RFQ, with solicitation in July 2026 and a Q4 2026 shortlist and PPCA target.
Tunnels Procurement Upcoming — No Timeline Set
HSRA lists a Tunnels procurement as upcoming with solicitation date and award timeline both TBD.
CAHSR Continues Construction Despite $86.8B Funding Shortfall
California High-Speed Rail is reported to be pushing forward with active construction while facing an $86.8 billion funding gap. The project's continuation despite this shortfall suggests ongoing need…
Funding Gap of $86.8B Creates P3 and Alternative Finance Opportunity Signal
The scale of the reported shortfall ($86.8B) far exceeds available state and federal funds, inferring that CAHSR will likely need to explore public-private partnership structures, private activity bon…
CA HSR Continues Operations Despite $86.8B Funding Shortfall
California high-speed rail is pushing forward with construction and program activities despite an $86.8 billion funding gap, per a June 2026 report. The project continues to advance without a fully fu…
California HSR cost estimate reportedly soars to $231 billion
A news report cites a new cost estimate of $231 billion for the California High-Speed Rail project, a significant increase over prior estimates. The article also references staff attrition, with worke…
CEO Delegation of Authority and Procurement Policies Revised
The CHSRA Board approved revisions to the CEO Delegation of Authority and Board RFQ/RFP policies at the June 24, 2026 meeting via Resolution #HSRA 26-11, including provisions requiring board approval …
Track and Systems Construction Contract (TSCC) Awarded
The Board approved award and execution of Contract HSR25-89 for Track and Systems Construction (Packages 1B and 2) at the June 1, 2026 meeting via Final Resolution HSR 26-07.
Program Budget and FY Baseline Approved — June 2026
The CHSRA Board approved the Program Budget Update and Fiscal Year Budget Authorization at the June 24, 2026 meeting via Resolution #HSRA 26-08, establishing the 2026 program baseline and FY spending …