← Back to signals
100

Track and Systems Contract Awarded to Kiewit/Stacy Witbeck/Herzog Consortium

procurement confirmed act_now
HSR Newsroom · Jul 05

Summary

The CAHSRA Board approved a consortium of Kiewit, Stacy Witbeck, and Herzog to install track, overhead contact system, train control, and communications infrastructure across 119 miles of Central Valley guideway. This is the initial phase of what was a $3.5B RFP issued in November 2025.

Details

Prime contract is awarded; subcontractor, specialty systems, and professional services opportunities are now active for electrification, train control, communications, and construction support work.

Up to $3.5B flowing to the Kiewit/Stacy Witbeck/Herzog consortium for track and systems installation

California High-Speed Rail Authority Kiewit Stacy Witbeck Herzog