Five Materials Contracts Awarded — Up to $507.1M NTP 1 Envelope Active
procurement
confirmed
watch
HSR Procurements · Sep 13
Linked Projects
Summary
The Authority has executed contracts for Long Welded Rail (HSR 25-26), Concrete Ties (HSR 25-27), OCS Poles (HSR 25-25), Cable Troughs (HSR 25-117), and Ballast (HSR 25-28), all under a cumulative NTP 1 ceiling of $507.1M.
Details
Awarded contracts signal active construction material delivery phase; subcontractors, logistics, and QA/QC service providers should pursue teaming opportunities with prime awardees.
Funds flowing to awarded rail materials suppliers for the 119-mile First Construction Section.
California High-Speed Rail Authority
—